50% INCREASE IN ORE RESERVES AT YANGIBANA PROJECT TO 7.74 MILLION TONNES

  • Probable Ore Reserves increased to 7.74 million tonnes at 1.13%TREO including 0.43%Nd2O3+Pr6O11
  • Includes the maiden Probable Ore Reserves at Yangibana West, Yangibana, Auer and Auer North deposits, estimated using JORC Code guidelines (2012 Edition)
  • These additional Ore Reserves confirm the eight-year mine life asdescribed in the Company’s Definitive Feasibility Study (DFS) ofNovember 2017
  • Drilling continuing to further increase Probable Reserves at Auer and Auer North

    Introduction

    Hastings Technology Metals Limited (ASX:HAS) is pleased to announce a significant increase in the Probable Ore Reserves at the Yangibana Project in the Gascoyne region of Western Australia. Total Probable Ore Reserves have increased to 7.74 million tonnes at 1.13%TREO including 0.43%Nd2O3+Pr6O11, a 50% increase on the figures established inNovember 2017 as part of the Company’s Definitive Feasibility Study (DFS) and as reported in the ASX release entitled “Successful Completion of Yangibana Definitive Feasibility Study” dated 28th November 2017.

    Probable Ore Reserves

    Based on Pre-Feasibility studies (PFS) for recent geological, geotechnical, metallurgical and environmental work, independent consultants Snowden Mining Industry Consultants (Snowden) has completed PFS mining studies based on Measured and Indicated Mineral Resources at the Yangibana West, Yangibana, Auer and Auer North deposits. The mining focus is high ore recovery, and conventional drill and blasting methods will be employed.

    The Modifying Factors used to estimate the Ore Reserves are provided in the Table 1 Section 4 of the JORC Code (2012) at the end of this announcement. Mining at each of the deposits will encounter three main rock types:

    • The upper horizon is a saprolite, this does not require blasting.
    • The lower weathered and fresh granite horizons require blasting.
    • Ironstone (not all of which is ore), RC grade control drilling is

      required.

The ore dips at between 10-45o and varies in thickness between 1m and 20m at Fraser’s and1m and 30m at Bald Hill, with an average thickness of 4m. At Yangibana West the ore dips at 20-40o and ranges to 5m thick. Ore at Yangibana is narrower at 2-3m and dips at 40-50o, and at Auer and Auer North it is steeper (70-80o) and averages around 3m wide.

The ore zone (generally ironstone) is visually distinct from the host rock, providing some visual control for ore identification. RC grade control drilling will be done, on a 10m x 10m grid, prior to ore delineation.

Well controlled blasting and mining near and in the ore zones is planned to minimise dilution and allow selective mining of the hanging-wall to expose and selectively mine the ore. Due to the high value of the ore, a high ore recovery is the focus of mining. As such, a 50cm skin of dilution is added to the ore mined to enable a 98% ore recovery assumption. This dilution was incorporated in the estimation of reserves at each deposit.

For pit optimisation a 28o overall wall angle was applied to the saprolite, and 35-40o to weathered and fresh granite. In addition to the 50cm skin applied during the resourcesestimation process, Snowden established waste dilution at 19% at Bald Hill, 14% at Fraser’s,32% at Yangibana West, 26% at Yangibana and 21% at Auer and Auer North. A 2% ore loss was also applied to each deposit.

Ground water at all deposits sits at around 45m below the mining surface. Pits will be dewatered ahead of mining using bores pumping a maximum 8 litres per sec pumped from each pit to provide a dewatered rock mass. Stormwater will be managed in pit using sumps with an estimated maximum of 10 litres per sec pumped from sumps in each pit.

Waste from each pit is stored in adjacent waste dumps. Some of the Bald Hill pit is backfilled to minimise haulage distances. Ore is transferred either directly to the Run-Of-Mine (ROM) pad, or to a low-grade stockpile, by mining trucks.

Pit optimisations were completed to determine the economic mining limits for each deposit. Only Measured and Indicated Resources were considered for processing. Pits were then designed in stages to enable higher grades to be targeted and waste extraction to be deferred.

Pit optimisation studies have defined the total Probable Ore Reserves for the Yangibana Project as shown in Table 1 including these additional deposits.

Deposit

Tonnes

%TREO

%Nd2O3+Pr6O11

Bald Hill

4,385,000

1.03

page2image5888016

0.41

page2image5890304

Fraser’s

780,000

1.58

0.67

Yangibana West

1,397,000

1.23

page2image5897584

0.34

Yangibana

838,000

0.99

page2image10000784

0.47

Auer

150,000

1.13

page2image7876176

0.41

page2image7878464

Auer North

192,000

1.22

0.45

TOTAL

7,742,000

1.13

0.43

Table 1 – Yangibana Project – Probable Ore Reserves July 2018

page3image3828416

The current resources at Auer and Auer North are shown in Tables 2 and 3 as reported in the ASX release entitled “Final 2017 JORC Resource Update Including Auer and Auer North Results” dated 22nd November 2017.

All Mineral Resources shown in the tables below are inclusive of Ore Reserves

Table 2 – Yangibana Project – Auer JORC Mineral Resources

Table 3 – Yangibana Project – Auer North JORC Mineral Resources

The current resources at Yangibana are shown in Table 4 as reported in the ASX releaseentitled “Yangibana Project Resources Now Exceed 20.5 Million Tonnes” dated 12th October 2017.

Table 4 – Yangibana Project – Yangibana JORC Mineral Resources

The current resources at Yangibana West are shown in Table 5 as reported in the ASX releaseentitled “Another Major Increase In JORC Resources From Current Yangibana Drilling” dated24th July 2017.

Table 5– Yangibana Project – Yangibana West JORC Mineral Resources

All Probable Ore Reserves are within tenements held 100% by Hastings, with all but those at Auer and Auer North being held under granted Mining Leases. The increased Ore Reserves support the eight-year mining and processing operation at 1.0 million tonnes per annum as described in the November 2017 DFS.

A major infill and extension drilling programme comprising both reverse circulation and diamond drilling is well advanced at Auer and Auer North aiming to increase estimates of Measured and Indicated Mineral Resources and thence reserves at these deposits.

Resource Category

Tonnes

%TREO

%Nd2O3+Pr6O11

Indicated

page3image5082320page3image3724720

261,000

1.17

0.42

Inferred

978,000

1.08

0.39

TOTAL

1,219,000

1.10

0.39

Resource Category

page3image9193184page3image3692896

Tonnes

%TREO

%Nd2O3+Pr6O11

page3image3779008

Indicated

301,000

1.24

0.45

Inferred

page3image7078560page3image5778400

460,000

0.96

0.30

TOTAL

page3image7087184page3image5867840page3image4991712page3image5054208

762,000

1.07

0.36

Resource Category

page3image9235408page3image1611968

Tonnes

%TREO

%Nd2O3+Pr6O11

Indicated

page3image7181488page3image3777968

1,318,000

0.86

0.41

Inferred

page3image9285360page3image3747392

851,000

page3image9198896page3image3749264

0.81

0.39

TOTAL

2,169,000

0.84

0.40

page3image5894464

Resource Category

Tonnes

%TREO

page3image3738240

%Nd2O3+Pr6O11

Indicated

1,686,000

1.29

0.35

Inferred

756,000

1.35

0.35

TOTAL

2,442,000

1.31

page3image3797520

0.35

page3image3760912

page4image3836256

Pre-Feasibility Study

The maiden Probable Ore Reserves at the Yangibana West, Yangibana, Auer and Auer North deposits are based on results of a supplementary Pre-Feasibility Study (PFS). Hastings undertook the PFS on these additional deposits, which are in addition to the Bald Hill andFraser’s deposits forming the Yangibana Rare Earths Project (the Project) in Western Australia.

The November 2017 Definitive Feasibility Study (DFS) detailed the Project, which will produce a Mixed Rare Earth Carbonate (MREC) rich in Neodymium (Nd) and Praseodymium (Pr), critical materials used in the manufacturing of permanent magnets. The DFS produced amaiden Ore Reserve for the Bald Hill and Fraser’s deposits, which underpinned the first 5 years of mine life. The DFS also included an additional production target (APT) produced from the Yangibana West, Yangibana, Auer and Auer North deposits.

The APT satellite deposits were not included in the 2017 Ore Reserve estimate because the required geotechnical investigation had not yet been completed and consequently the mine design and mining cost estimates could not be developed to a PFS level. The required geotechnical drilling and analysis was then completed in Q2 2018 and mine designs were also completed. Metallurgical development was substantially completed in 2017, except for comminution test work and confirmation of the compatibility of the Yangibana West deposit with the DFS process plant flowsheet. This work has since been undertaken to the required pre-feasibility level.

The Project is comprised of significant deposits across the tenement holdings – Bald Hill, Fraser’s, Yangibana West, Yangibana, Auer and Auer North – all 100% owned by Hastings (note that these areas mentioned herein represent approximately 50sqkm out of a total of 650sqkm of exploration tenure). In addition, Hastings holds a controlling 70% stake in other tenements held in a Joint Venture arrangement in the greater Yangibana area, although these have not been considered in this PFS study. These Joint Venture tenements may be readily developed as upside to increase the mine life of the Project in the future.

The 2017 DFS evaluated the development of the mine, process plant (incorporating beneficiation and hydrometallurgy) and supporting infrastructure. The Project is designed to mine 1 Million tpa of ore and a process plant that can produce up to 15,000t of Mixed Rare Earths Carbonate (MREC) per annum from the Bald Hill, Frasers, Yangibana West, Yangibana, Auer and Auer North deposits. The current Ore Reserves of 7.74 Million tonnes supports a mine life of 8 years.

Hastings has completed the following work on the site:

  • Mapping,
  • Rock chip sampling,
  • Commissioned a major hyperspectral survey,
  • Topographic and aerial photo surveys, and
  • Aeromagnetic and radiometric survey and interpretation over the GCFC.
page5image3865152

Seven phases of drilling – both reverse circulation and diamond drilling have been completed by Hastings, with each phase increasing the JORC resources of the various deposits and providing samples for metallurgical test work. With shallow mineralisation, mining will be conventional drill and blast and operated by a mining contractor.

Figure 1 – Yangibana Project Layout Plan

The Company has completed extensive DFS testwork to define the metallurgy for the Yangibana project, culminating in pilot plant tests on a composite sample of material fromBald Hill and Fraser’s. This testwork has defined a process route entailing crush, grind, flotation, acid bake with water leach and precipitation of a Mixed Rare Earths Carbonate. Further metallurgical PFS testwork has established that the ore from each of Yangibana West, Yangibana, Auer and Auer North is compatible with this processing route.

Approximately 1 million tonnes per annum of ore will be brought to the Run Of Mine (ROM) pad where the flowsheet process begins. Early stages of the processing of the ore comprise comminution and beneficiation. The resulting beneficiated concentrate is upgraded by 20 times from the ROM ore, as demonstrated through the DFS, to a 25% TREO concentrate. This concentrate is further processed downstream through a hydrometallurgical process that involves acid bake, water leaching, impurity removal and precipitation to produce up to 15,000 tpa of MREC. The MREC will contain up to 3,400 tpa of neodymium oxide (Nd2O3) + praseodymium oxide (Pr6O11) representing 41% of contained TREO.

The scope of work required for environmental approvals have been substantially completed and the Project is progressing through a Public Environmental Review (PER) level of

page5image3879936

page6image3893152

assessment by both the State and Commonwealth Governments. Auer and Yangibana deposits will require additional approval considerations as a formality although environmental considerations in the PFS demonstrated no significant environmental issues that would preclude a future approval being issued by State and Commonwealth Governments.

The key Ore Reserve parameters developed from the supplementary PFS are shown in Table 6 below.

Pre-Feasibility Study Parameters

Parameter

Status of JORC Resources used for financial evaluation

Measured and Indicated

Mining Method

Open Pits

Mining Dilution – 0.5m skin on HW and FW incorporated in resource estimation

variable

Mining Recovery

98%

Processing Route

Flotation, Acid Bake – Water Leach and MREC Precipitation

Overall Processing Recovery (TREO) – Ore to MREC

page6image9188816

75.2%

Target Production Rate (Mixed Rare Earths Concentrate)

15,000 tpa

Target Contained Nd2O3+Pr6O11

page6image7108576

3,400 tpa

Pre-Production Capital Costs

A$335.3m

page6image9280656

Production Capital Costs

A$13.1m

Operating Costs

page6image9202032

A$18.5/kgTREO

Basket Value of MREC product

US$29.21/kgTREO

Exchange Rate US$:A$

0.75

page6image11316992

Discount Rate

page6image7194480

8%

Table 6– Yangibana Project – PFS Ore Reserve Parameters

This PFS financial evaluation evaluates the production targets based only on the combinedBald Hill, Fraser’s, Yangibana, Yangibana West, Auer and Auer North deposits that wereupgraded through the DFS and this PFS to a Probable Ore Reserve of 7,742 Mt (DFS Production Target).

A summary of the Mineral Resources and their utilisation as Production Target in the financial evaluation is provided in Table 7 below.

page7image3924064

Deposit

Mineral Resources (t)

Production Target (t)

Measured

Indicated

Inferred

Total

2017 DFS + 2018 PFS Production Target from Probable Ore Reserve

Bald Hill

2,700,000

2,050,000

1,340,000

6,100,000

4,385,000

Fraser’s

220,000

650,000

700,000

1,580,000

780,000

Auer

260,000

960,000

page7image5099680

1,220,000

page7image3800432

150,000

Auer North

300,000

460,000

760,000

192,000

Yangibana

1,180,000

720,000

1,900,000

838,000

Yangibana West

110,000

1,660,000

page7image9268560

760,000

page7image1698080

2,540,000

1,397,000

Total

3,030,000

6,100,000

page7image9239664page7image9241232

4,940,000

page7image5836224 page7image9204720

14,100,000

7,472,000

Table 7– Yangibana Project – PFS Production Target Resources

Resources shown do not represent the total Mineral Resources and are inclusive of Ore Reserves. Deposits not used in the economic evaluation have been excluded from Mineral Resources. Rounding errors may appear

The PFS financial model assumes an average long-term US$/A$ exchange rate of US$0.75 and uses price forecasts from 2017 to 2027 for rare earths prices from Argus Media, an independent provider of price information, market data and business intelligence for the global resource industry. Financial evaluation of the Probable Ore Reserves in the PFS results in the economic outcome shown in Table 8 below.

Table 8– Yangibana Project – PFS Financial Evaluation Results

TERMINOLOGY USED IN THIS REPORT

Total Rare Earths Oxides, TREO, is the sum of the oxides of the light rare earth elements lanthanum (La), cerium (Ce), praseodymium (Pr), neodymium (Nd), and samarium (Sm) and the heavy rare earth elements europium (Eu), gadolinium (Gd), terbium (Tb), dysprosium (Dy), holmium (Ho), erbium (Er), thulium (Tm), ytterbium (Yb), lutetium (Lu), and yttrium (Y).

For further information please contact:

Stefan Wolmarans, Chief Operating Officer, +61 2 9078 7674 Andy Border, General Manager Exploration, +61 2 9078 7674

Please follow and like us:
0

Hits: 30

Leave a Reply

Your email address will not be published. Required fields are marked *